| |
ELECTRICAL
WORLD,
December 1985
BAD
INSULATORS POSE HIDDEN THREAT
A common assumption is that defective suspension insulators on
a transmission line can readily be identified either visually
or by visual inspection coupled with a knowledge of local conditions.
However, the, results of a systematic program of testing energized
suspension insulators in situ, conducted over a period of almost
10 years by West Kootenay Power & Light Co. Ltd., British Columbia,
Canada, shows that the majority of defective insulators of this
type reveal no externally visible symptoms.
West
Kootenay's current test program began when a 55-mi, 60-kV line
that had previously exhibited good reliability began to experience
unexplainable trips, usually after precipitation had occurred.
Reclosing was successful, and patrols on foot and by helicopter
failed to detect any causes. Finally, in 1975, the circuit failed
and locked out, and though patrols again failed to uncover a cause,
a rural customer detected a flashover of the center string on
a vertical running corner. This string was replaced and the line
successfully reclosed. The insulators in the string appeared to
be perfectly normal but tested defective, so the company became
convinced that invisible insulator failures were causing the trips.
Because
every string on the line had been closely inspected visually,
the company tried several other methods to detect these invisible
failures. Each string was scanned by a large parabolic microphone
with a frequency divider. Unfortunately, every string was found
to be noisy.
Because
every string on the line had been closely inspected visually,
the company tried several other methods to detect these invisible
failures. Each string was scanned by a large parabolic microphone
with a frequency divider. Unfortunately, every string was found
to be noisy.
Every
string was then examined using an infrared detector, looking for
signs of heat generated by leakage current. None was found.
Linemen
measured voltage drop across each insulator in a string, using
phasing sticks, and the results were plotted on the assumption
that a voltage drop would fall within predictable limits, depending
on where in the string the insulator was located. The results
were inconclusive.
Working
with a prototype of the Hi-Test Detection Instrument, West Kootenay
developed a tester designed to duplicate, on an energized line,
the conventional shop test. That test "meggered" resistance
at 10 kV and rejected any unit with less-than-infinite resistance.
The tester that has evolved from that prototype is a self-contained,
HVDC power source that is unaffected by ac voltages of up to 30
kV across its test probes. It imposes a 10-kV test voltage across
the test points and measures the resultant current flow. It can
be powered either by a 120-V-ac or a 12-V-dc source, and is light
enough to be used by a single lineman at the end of a standard
hot stick. A current-limiting feature prevents shock to personnel
even at the 10 kV across the probes.
When
the early prototype of the tester was put into service on the
line, the results were startling. Over a third of the insulators
tested on nontangent structures showed as defective, and subsequent
laboratory tests confirmed the results. By 1978, all insulators
shown as defective by the field test had been replaced. Since
that time, not one trip attributable to a suspension insulator
has been experienced.
Recent
experience
Live-line
crews recently were called upon to replace a dead-end string believed
to have been damaged by rifle fire. The string was on a 170kV
line, 88 ml long, constructed in 1965 using 15.kip insulators
supplied by several manufacturers. The insulators were installed
in strings of twelve and supported 477-kcmil Hawk conductor with
a normal tension of 4,000 lb.
Examination
of the broken shells of the seven insulators that lay on the ground
revealed that they had not been shot, but were broken almost exactly
in half. Using the tester, the crew determined that only three
of the remaining five insulators in the string remained electrically
effective, so both ends of the string had to be considered hot
during changeout.
West
Kootenay now routinely tests suspension insulators on nontangent
structures to determine that they can be safely hot-sticked before
any live-line procedure is undertaken. Frequently, insulator conditions
discovered are such that routine live-line procedures would place
the line men at risk.
Each
string is tested by a pair of line men, one who operates the tester
and one who records the data on a standard form, starting at the
structure and proceeding towards the conductor. If an insulator
tests defective, then a second reading is taken across the porcelain
to measure surface contamination. With the exception of some insulators
in an area of known contamination, all insulators that have tested
defective registered zero deflection across the skirt and full
deflection from pin to cap, Average test time is 13 minutes per
structure. Previous testing has convinced the company that failures
on tangent structures are sufficiently rare so as not to justify
testing of those structures at this time.
The
test procedure stipulates that testing of a particular string
stop when a sufficient number of defective units had been found
so that the voltage to ground divided by the number of remaining
untested insulators would yield 30 kV or higher.
Tests
are not conducted on noisy strings, which indicate high electrical
stress. These measures are designed to protect the linemen and
to avoid triggering a flashover.
Test
results

A
total of 84 structures on the aforementioned 88-mi line were tested,
including 30 running corners and 54 dead-ends. Corrective action
was needed on 42 of the structures. The data from these tests
support the conclusions discussed below.
Table
I: Position in string |
Position |
No.
of defectives |
1(at
structure) |
22 |
2 |
16 |
3 |
26 |
4 |
16 |
5 |
28 |
6 |
22 |
7 |
28 |
8 |
28 |
9 |
23 |
10 |
21 |
11 |
17 |
12(at
conductor) |
10 |
Table
II: Failure by structure type |
Structure |
No.
of
insulators
used |
No.
of
defects
found |
Probability
of defect |
Running
corner |
1080 |
6 |
0.01 |
Horiz.
dead-end |
3222 |
199 |
0.06 |
Up-hill
dead-end |
240 |
67 |
0.28 |
Downhill
dead-end |
252 |
0 |
0.00 |
Jumper |
887 |
20 |
0.02 |
Total |
5681 |
295 |
0.05 |
Table
III: Defective units per string |
No.
defective |
No.
strings |
Probability
of defect |
1
or more |
115 |
0.28 |
2
or more |
75 |
0.65 |
3
or more |
44 |
0.59 |
4
or more |
31 |
0.70 |
5
or more |
17 |
0.55 |
6
or more |
13 |
0.76 |
7
or more |
5 |
0.38 |
-
Suspension
insulators fail in service in ways that give no visual indication.
A total of 5,681 insulators tested produced 295 defective units.
This does not include those with defects capable of visual identification,
such as broken skirts, flash marks or cracks. In other words,
all insulators identified as defective by the tester bore no
visible signs that they were defective. This is consistent with
the results of all previous testing programs within the company.
Sectioning the defective insulators invariably showed cracks
that penetrated through the porcelain under the cap (Fig I).
-
Failure
is random with respect to position in a string. A common belief
in the industry is that the insulator closest to the conductor
is the one most likely to fail. This is not supported by the
test data. (Table I). A Chi Square analysis of these data gives
the value of X2 as 20.0638. At 11 deg of freedom
and 00=0.02, X2 =22.618. These values
indicate that the occurrence of defects in a string is random
with respect to position relative to the conductor.
-
Defective insulators are not randomly distributed throughout
the line. Tangent structures rarely have defective insulators.
The test data suggest several additional ways in which defective
units seem to be concentrated (Table II). Although the demonstrated
average probability of finding a defect is P = 0.05 for all
insulators tested, the probability varies by type of structure
from a low of P = 0.00 on down hill dead-ends to a high of P
= 0.28 on up hill dead-ends.
The following hypotheses are advanced for possible consideration.
-
First, the greater the exposure of the cement bonding to
moisture and contamination, the higher the incidence of
failure. Note that there is an extremely low incidence of
failure on tangent structure where the insulator strings
hang vertically and varying higher probabilities of failures
for different configurations having varying degrees of exposure.
Note
also the data on uphill and down hill dead-end strings
in Table II. The probability of finding failures in the
uphill strings is a high 0.28, compared to essentially
zero for downhill strings. The structures represented
by these data are located on mountainsides such that the
uphill strings have a high exposure and the downhill strings
a low exposure.
-
A second hypothesis is that the greater the mechanical stress,
the higher the incidence of failure. The test program produced
some interesting information regarding stress to which the
insulators might be exposed-but not stress of the kind imposed
by operating conditions. Three anomalies appeared in the
test data. First, all nine of the defective units on running
corners were found on one particular corner out of 30 tested.
Also, of the 20 defective units found in 84 jumper strings,
four were in one particular string, and three in another.
Mechanical
stress that could damage the insulators might be imposed
by:
- Missing
or improperly located vibration dampers
- heavy
snow loading, or
- improper
handling during installation.
Discussions
with the crew that had constructed the line revealed that
the strings in question might have been hoisted into position
by a hitch secured at the center of the string. During
the hoist, the line occasionally slipped, letting the
string fall free for several feet before it was jerked
to a stop. It is not unreasonable to suspect that this
shock load might cause pin-to-cap cracking, although the
data are not adequate to support this hypothesis.
-
The
nonrandom distribution of failures poses a significant hazard
to both reliability and personnel safety. A cursory review of
the data could lead to the erroneous conclusion that the overall
incidence of insulator failure is so low as to pose no hazard
to system reliability or the safety of personnel. With a probability
of failure of any insulator being only 0.05, and the situation
with the worst probability of failure-that occurring at dead-ends--affecting
only seven structures out of 84, there doesn't appear to be
a significant threat.
Further
analysis, however, disproves this. Using the full string as
the unit of analysis, there appears to be a "cascading"
effect of failure within a string (Table III).
Using
the string as the basic unit of analysis, the probability
of finding at least one faulty insulator in that string is
P = 0.28. This is based on the test of 414 strings (excluding
the running corners that may have been overstressed during
installation - see above), of which 115 had at least one defective
unit. This is a very large increase over the probability calculated
with the individual insulator as the basic unit. What is significant
with respect to the reliability of the line and the safety
of personnel is what happens to the probability of finding
additional defective units in a string once the first one
has been found.
Given
that at least one in the string is defective, the probability
that there are more rises to P = 0.65.
Given
that at least two defective units have been found in a string,
the probability that there are more is P = 0.59.
Table
III lists the probabilities associated with the higher incidences
of defective units.
These
results demonstrate the cascading effect that says that once
one defective insulator has been found in a string, the probability
of finding more in that string increases significantly and
remains high right up to the point where enough are defective
to pose a hazard to reliability and safety.
To
illustrate the potential loss of reliability, the data show
that, on the 88-MI line in this analysis, there were 31 strings
where the insulation level had been reduced to 67% or less
of installed values, and, of these, 13 were at less than 50%
of installed value.
From
a safety viewpoint, standard operating procedures to service
the insulators on the same line would have created a situation
where the level of insulation was reduced by 50% or more on
24 strings and by 60% or more on 13 of those strings. The
defective insulators show no visible signs of defects, and
would have appeared to the line crew to be functioning normally.
Go
to the IT-4 Insulator Tester product page
<top
of article>
|
|